Which of the following actions should the project manager take NEXT?

The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Obtain additional approval from the project sponsor.

B.
Discuss this change during the next status meeting.

C.
Perform a probability and impact analysis on the change.

D.
Create a plan to implement the change.