Which of the following is the FINAL step in the pre-project setup phase?

Which of the following is the FINAL step in the pre-project setup phase?

PrepAway - Latest Free Exam Questions & Answers

A.
Obtain signed approval of the project charter.

B.
Obtain signed approval of the statement of work (SOW).

C.
Conduct a feasibility analysis for the project.

D.
Create the work breakdown structure (WBS).