you need to include in your risk contingency fund?

You are the project manager of the NHH project for your company. You and the project team have
completed the quantitative risk analysis for your project. During this process you create a
contingency reserve based on the risk probability-impact matrix as seen in the figure below.

Based on the information in the figure above, what amount would you need to include in your risk
contingency fund?

PrepAway - Latest Free Exam Questions & Answers

A.
-$465,000

B.
$171,500

C.
-$258,500

D.
$258,500