PrepAway - Latest Free Exam Questions & Answers

What is the cost performance index for this project to determine if the contingency response should happen?

Pete works as a project manager for BlueWell Inc. The Management has told him that he must
implement an agreed-upon contingency response if the cost performance index in his project is
less than 0.90. Consider that Pete’s project has a budget at completion of $275,000. His project is
65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78
percent complete. What is the cost performance index for this project to determine if the

contingency response should happen?

PrepAway - Latest Free Exam Questions & Answers

A.
1.02

B.
0.96

C.
0.90

D.
0.89


Leave a Reply