You work as a project manager for SoftTech Inc. You are working with the project stakeholders to
begin the qualitative risk analysis process. Which of the following inputs will be needed for the
qualitative risk analysis process in your project? Each correct answer represents a complete
solution. Choose all that apply.

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assets

B.
Cost management plan

C.
Project scope statement

D.
Risk register