Which of the following statements best describes the level of detail Lisa should include with the risk respons
Lisa is the project manager of the SQL project for her company. She has completed the risk
response planning with her project team and is now ready to update the risk register to reflect the
risk response. Which of the following statements best describes the level of detail Lisa should
include with the risk responses she has created?
What should Jenny do with these risk events?
Jenny is the project manager for the NBT projects. She is working with the project team and
several subject matter experts to perform the quantitative risk analysis process. During this
process she and the project team uncover several risks events that were not previously identified.
What should Jenny do with these risk events?
Which project management plan will define who will be available to share information on the project risks?
[tagged]
You work as the project manager for Bluewell Inc. Your project has several risks that will affect
several stakeholder requirements. Which project management plan will define who will be
available to share information on the project risks?
what term?
[tagged]
You work as a project manager for BlueWell Inc. Your project is using a new material to construct
a large warehouse in your city. This new material is cheaper than traditional building materials, but
it takes some time to learn how to use the material properly. You have communicated to the
project stakeholders that you will be able to save costs by using the new material, but you will
need a few extra weeks to complete training to use the materials. This risk response of learning
how to use the new materials can also be known as what term?
What will Jenny reply to you?
Jenny is the project manager of the NHJ Project for her company. She has identified several
positive risk events within the project and she thinks these events can save the project time and
money. You, a new team member wants to know that how many risk responses are available for a
positive risk event. What will Jenny reply to you?
Which part of your project is most likely to have a uniform risk distribution?
[tagged]
You are working with Anna on your project to determine and map the probability distributions of
risk within the project. You have indicated that you will use the uniform distribution method for a
portion of the project. Which part of your project is most likely to have a uniform risk distribution?
Which one of the following risk identification approaches is an information gathering technique?
[tagged]
You are the project manager of the GYH project for your organization. Management has asked
you to begin identifying risks and to use an information gathering technique. Which one of the
following risk identification approaches is an information gathering technique?
Who is correct in this scenario?
Sammy is the project manager for her organization. She would like to rate each risk based on its
probability and affect on time, cost, and scope. Harry, a project team member, has never done this
before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk
score should be created, not three separate risk scores. Who is correct in this scenario?
What happens when the project manager crashes a project?
Your organization has named you the project manager of the JKN Project. This project has a BAC
of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule
baseline has a variance of more than five percent then you will need to crash the project. What
happens when the project manager crashes a project?
Which one of the following is the only thing that the risk identification process will create for Kelly?
[tagged]
Kelly is the project manager of the BHH project for her organization. She is completing the risk
identification process for this portion of her project. Which one of the following is the only thing that
the risk identification process will create for Kelly?