What risk event is most appropriate?

You are the program manager for your organization. Management is considering a new program
but they are worried about the program risks that may affect the program success. You know that
there are three positive risks responses and three negative risk responses that each risk can have.
Management asks you which risk response would be most appropriate for a large risk event if they
wanted to hire a third-party to own the risk event for the program. What risk event is most
appropriate?

What risk response has been enacted in this project?

Bill is the project manager of the JKH Project. He and the project team have identified a risk event
in the project with a high probability of occurrence and the risk event has a high cost impact on the
project. Bill discusses the risk event with Virginia, the primary project customer, and she decides
that the requirements surrounding the risk event should be removed from the project. The removal
of the requirements does affect the project scope, but it can release the project from the high risk
exposure. What risk response has been enacted in this project?

Which one of the following is a valid response to the identified risk event?

[tagged]
Your project team has identified a project risk that must be responded to. The risk has been
recorded in the risk register and the project team has been discussing potential risk responses for
the risk event. The event is not likely to happen for several months but the probability of the event
is high. Which one of the following is a valid response to the identified risk event?

What risk response has Holly used in this instance?

Holly is the project manager of the GHH Project. During risk identification and the subsequent risk
analysis process she has identified a risk with a high probability and high impact for her project.
She and the stakeholder agree that the project management plan should be changed to eliminate
the risk threat entirely. What risk response has Holly used in this instance?