Mary is a project manager in her organization. On her current project she is working with her
project team and other key stakeholders to identify the risks within the project. She is currently
aiming to create a comprehensive list of project risks so she is using a facilitator to help generate
ideas about project risks. What risk identification method is Mary likely using?

PrepAway - Latest Free Exam Questions & Answers

A.
Brainstorming

B.
Delphi Techniques

C.
Checklist analysis

D.
Expert judgment