What is the project’s schedule performance index?

You are the project manager of the NNH Project. In this project you have created a contingency
response that the schedule performance index should be less than 0.93. The NHH Project has a
budget at completion of $945,000 and is 45 percent complete though the project should be 49
percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.
What is the project’s schedule performance index?

PrepAway - Latest Free Exam Questions & Answers

A.
-$37,800

B.
0.93

C.
0.92

D.
1.06