what is the risk exposure of the event that must be considered for the cost of the risk response?

You are the project manager of the KJH Project and are working with your project team to plan the
risk responses. Consider that your project has a budget of $500,000 and is expected to last six

months. Within the KJH Project you have identified a risk event that has a probability of .70 and
has a cost impact of $350,000. When it comes to creating a risk response for this event what is the
risk exposure of the event that must be considered for the cost of the risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
The risk exposure of the event is $245,000.

B.
The risk exposure of the event is $500,000.

C.
The risk exposure of the event is $350,000.

D.
The risk exposure of the event is $850,000.