You are the project manager of the BlueStar project in your company. Your company is structured
as a functional organization and you report to the functional manager that you are ready to move
onto the qualitative risk analysis process. What will you need as inputs for the qualitative risk
analysis of the project in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitative risk analysis does not happen through the project manager in a functional structure.

B.
You will need the risk register, risk management plan, project scope statement, and any
relevant organizational process assets.

C.
You will need the risk register, risk management plan, outputs of qualitative risk analysis, and
any relevant organizational process assets.

D.
You will need the risk register, risk management plan, permission from the functional manager,
and any relevant organizational process assets.