Which of the following types of risk response are you following?

You are the project manager for a construction project. The project involves casting of a column in
a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill
will be required for casting that column. You decide to hire a local expert team for casting that
column. Which of the following types of risk response are you following?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance

B.
Avoidance

C.
Mitigation

D.
Transference