[tagged]
You are the project manager of RTF project for your organization. You are working with your
project team and several key stakeholders to create a diagram that shows causal factors for an
effect to be solved. What diagramming technique are you using as a part of the risk identification
process?

PrepAway - Latest Free Exam Questions & Answers

A.
Cause and effect diagrams

B.
System or process flow charts

C.
Predecessor and successor diagramming

D.
Influence diagrams