Which modeling technique can help Frances to accomplish this goal?

[tagged]
Frances is the project manager of a project in her organization. This project has a budget of
$567,000 and is schedule to last for three years. Frances wants to examine the risk events to
determine which risk events have the most potential impact on the project. Which modeling
technique can help Frances to accomplish this goal?

PrepAway - Latest Free Exam Questions & Answers

A.
Expected monetary value

B.
Sensitivity analysis

C.
Quantitative risk analysis

D.
Modeling and simulation