Rex is the project manager of the BDF Project. This project will last for two years and has a
budget of $2,345,000. Management has instructed Rex that the project must not go over budget
as funds are very tight in the organization. During the project planning Rex and the project team
discover a positive risk event to save $75,000. Rex wants to make certain that this risk event
happens so which risk response method is most appropriate?
A.
Share
B.
Mitigation
C.
Exploit
D.
Enhance