Why must risk attitude be considered as a part of risk analysis?

Todd is the project manager of the EST project for his company. His organization has established
certain rules in the enterprise environmental factors which affect the approach that Todd takes in
managing his project. One of the rules requires Todd to consider the risk attitude of the
stakeholders participating in risk analysis. Why must risk attitude be considered as a part of risk
analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk attitude can affect the measurement of probability and impact.

B.
Risk attitude can establish a stakeholder’s influence over project decisions.

C.
Risk attitude identifies stakeholders that are hygiene seekers or motivation seekers.

D.
Risk attitude establishes stakeholders as positive or negative stakeholders.