4 Comments on “Which project document is updated in the Control Stakeholder Engagement process?

    1. William says:

      I agree with ibacs as the best answer is D. As part of project documents updates you could run into issues that need to be added to the issue log; however, the best answer is Work Performance Information.




      0



      0
  1. Naren says:

    The Answer is D. Issue log is input to Control Stakeholder Engagement.

    Work performance information is one of the output if Control stakeholder Engagement.

    Ref; PMBOK 5 page# 410