PrepAway - Latest Free Exam Questions & Answers

Which of the following is a tool and technique for activity duration estimating?

Which of the following is a tool and technique for activity duration estimating?

PrepAway - Latest Free Exam Questions & Answers

A.
Parametric estimating
Functional

B.
Monte Carlo analysis
Projectized

C.
Top-down estimating
Weak Matrix

D.
Bottom-up estimating
Balanced Matrix

A.
Parametric estimating
Functional

B.
Monte Carlo analysis
Projectized

C.
Top-down estimating
Weak Matrix

D.
Bottom-up estimating
Balanced Matrix

Explanation:
QUESTIONNO: 734
A project manager’s authority is limited within which of the following organizational structures?

One Comment on “Which of the following is a tool and technique for activity duration estimating?


Leave a Reply