PrepAway - Latest Free Exam Questions & Answers

5 Comments on “Which process should be conducted from the project inception through completion?

  1. Don says:

    Correct Answer
    A – Monitor and control should be performed through all the life cycle of the project. So at completion, this process should be performed.

    Wrong Anwers
    B- Perform Quality Control is part of the Monitor and control Project Work. it is not the best choice

    C-Approving the changes are done in this process. in the question, nothing mentioned is related to changes should be approved or done.

    D- monitor and control Risk is part of Monitor and control Project Work. Also, at the completion of the project, the risks are lower. it is not the best choice.




    0



    0
  2. Bryan says:

    C is the answer is correct

    Perform Integrated Change Control
    This is the process of reviewing all change requests, approving changes and managing changes to the deliverables, organizational process assets, project documents and the project management plan. It is conducted from project inception through completion because no matter how carefully planned a project has been, changes will need to be made throughout its life cycle. – See more at: http://www.free-management-ebooks.com/faqpm/integration-06.htm#sthash.L89ff1DB.dpuf




    0



    0

Leave a Reply