Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted
resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a
critical EVM metric?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost variance (CV)

B.
Cost performance index (CPI)

C.
Budget at completion (BAC)

D.
Variance at completion (VAC)