PrepAway - Latest Free Exam Questions & Answers

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Which process involves aggregating the estimated costs of the individual schedule activities or
work packages?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate Costs

B.
Estimate Activity Resources

C.
Control Costs

D.
Determine Budget

3 Comments on “Which process involves aggregating the estimated costs of the individual schedule activities or work packages?


Leave a Reply