The process of monitoring the status of the project to update project progress and manage changes to the sched

The process of monitoring the status of the project to update project progress and manage
changes to the schedule baseline is:

PrepAway - Latest Free Exam Questions & Answers

A.
Control Schedule.

B.
Quality Control.

C.
Perform Integrated Change Control.

D.
Develop Schedule.

One Comment on “The process of monitoring the status of the project to update project progress and manage changes to the sched

  1. Adeeb says:

    Control Schedule—The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
    Page 141 PMBook.