One Comment on “Which of the following is an output of Direct and Manage Project Execution?

  1. Biswaranjan Behera says:

    according to PMBOK5, answer should be “work performance data”.
    It’s been noted that these questionnaires in this site is using term “work performance information” as “work performance data”, but according to PMBOK5, both the terms are different.