This issue could have been avoided if they had created and followed a:

A project team attempts to produce a deliverable and finds that they have neither the expertise nor
the time to complete the deliverable in a timely manner. This issue could have been avoided if
they had created and followed a:

PrepAway - Latest Free Exam Questions & Answers

A.
risk management plan

B.
human resource management plan

C.
scope management plan

D.
procurement management plan