Which illustrates the connection between work that needs to be done and its project team members?

Which illustrates the connection between work that needs to be done and its project team
members?

PrepAway - Latest Free Exam Questions & Answers

A.
Work breakdown structure (WBS)

B.
Network diagrams

C.
Staffing management plan

D.
Responsibility assignment matrix (RAM)