The technique of subdividing project deliverables into smaller, more manageable components until the work and

The technique of subdividing project deliverables into smaller, more manageable components until
the work and deliverables are defined to the work package level is called:

PrepAway - Latest Free Exam Questions & Answers

A.
a control chart.

B.
baseline.

C.
Create WBS.

D.
decomposition.