Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, col

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate
generation, collection, distribution, storage, retrieval, and ultimate disposition of project
information?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Integration Management

B.
Project Communications Management

C.
Project Information Management System (PIMS)

D.
Project Scope Management