PrepAway - Latest Free Exam Questions & Answers

Which one of the following is NOT an input to the risk identification process?

You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality management plan

B.
Cost management plan

C.
Procurement management plan

D.
Stakeholder register

Explanation:

The procurement management plan is not one of the eleven inputs for the risk identification process. The eleven inputs to this process are. risk management plan, activity cost estimates, activity duration estimates, scope baseline, stakeholder register, cost management plan, schedule management plan, quality management plan, project documents, enterprise environmental ors, and organizational process assets.
What is the procurement management plan?
The procurement management plan defines more than just the procurement of team members, if needed. It defines how procurements will be planned and executed, and how the organization and the vendor will fulfill the terms of the contract.
Answer option D is incorrect. The stakeholder register is an input to the risk identification process. Answer option B is incorrect. The cost management plan is an input to the risk identification process. Answer option A is incorrect. The quality management plan is an input to the risk identification process. Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"

One Comment on “Which one of the following is NOT an input to the risk identification process?


Leave a Reply