PrepAway - Latest Free Exam Questions & Answers

Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?

You are the project manager of a large project that will last four years. In this project, you would like to model the risk based on its distribution, impact, and other ors. There are three modeling techniques that a project manager can use to include both event-oriented and project-oriented analysis. Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?

PrepAway - Latest Free Exam Questions & Answers

A.
Expected monetary value

B.
Sensitivity analysis

C.
Jo-Hari Window

D.
Modeling and simulation

Explanation:

The Jo-Hari window is not a risk modeling tool. It is a cognitive exercise to identify communication and relationship for individuals and team dynamics.
Answer option B is incorrect. Sensitivity analysis is a modeling technique used during the quantitative risk analysis process.
Answer option A is incorrect. Expected monetary value is a modeling technique used during the quantitative risk analysis process.
Answer option D is incorrect. Modeling and simulation is a modeling technique used during the quantitative risk analysis process.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"

One Comment on “Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?


Leave a Reply