PrepAway - Latest Free Exam Questions & Answers

what type of risk response?

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance

B.
Transference

C.
Mitigation

D.
Avoidance

Explanation:

Transference is a strategy to mitigate negative risks or threats. In this strategy, consequences and the ownership of a risk is transferred to a third party. This strategy does not eliminate the risk but transfers responsibility of managing the risk to another party. Insurance is an example of transference. When Gary

hires a professional vendor to manage that risk, the risk event does not go away but the responsibility for the event is transferred to the vendor.
Answer option D is incorrect. Avoidance removes the risk event entirely either by adding additional steps to avoid the event or reducing the project scope requirements.

Answer option C is incorrect. Mitigation are actions Gary’s project team could take to reduce the probability and/or impact of a risk event.
Answer option A is incorrect. Gary is not accepting this risk event, he does not want anyone on his team to become injured so he’s transferring the event.
Reference: Chapter 11. A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth Edition, ISBN.9781933890517, Section 11.5.2.1.