You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk management plan

B.
Stakeholder register

C.
Project scope statement

D.
Risk register

Explanation:

You would not need the stakeholder register to perform qualitative risk analysis. Qualitative Risk Analysis uses the likelihood and impact of the identified risks in a fast and cost-effective manner. Qualitative Risk Analysis establishes a basis for a focused quantitative analysis or Risk Response Plan by evaluating the precedence of risks with a concern to impact on the project’s scope, cost, schedule, and quality objectives. The qualitative risk analysis is conducted at any point in a project life cycle. The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical response. The inputs to the Qualitative Risk Analysis process are.
Organizational process assets
Project Scope Statement
Risk Management Plan
Risk Register
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"