Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

You work as a project manager for TechSoft Inc. You are working with the project stakeholders onthe qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Reassessment

B.
Risk Categorization

C.
Risk Urgency Assessment

D.
Risk Data Quality Assessment