PrepAway - Latest Free Exam Questions & Answers

What is the project’s schedule performance index?

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.

What is the project’s schedule performance index?

PrepAway - Latest Free Exam Questions & Answers

A.
1.06

B.
0.92

C.
-$37,800

D.
0.93


Leave a Reply