which one?

The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Watchlist of low-priority risks

B.
Risk probability-impact matrix

C.
Trends in qualitative risk analysis

D.
Risks grouped by categories

Explanation:

The risk matrix is not included as part of the risk register updates. There are seven things that can be updated in the risk register as a result of qualitative risk analysis. relating ranking of project risks, risks grouped by categories, causes of risks, list of near-term risks, risks requiring additional analysis, watchlist of low-priority risks, trends in qualitative risk analysis.
Answer option D is incorrect. Risks grouped by categories are part of the risk register updates. Answer option A is incorrect. Watchlist of low-priority risks is part of the risk register updates. Answer option C is incorrect. Trends in qualitative risk analysis are part of the risk register updates. Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth edition"