What type of a chart is management asking you to create?

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

PrepAway - Latest Free Exam Questions & Answers

A.
Work breakdown structure

B.
RACI chart

C.
Resource breakdown structure

D.
Roles and responsibility matrix

Explanation:

A resource breakdown structure is a visual diagram depicting the resources that will be used within the project.
Answer option A is incorrect. The work breakdown structure is a visual diagram of the project deliverables the project will create.
Answer option D is incorrect. The roles and responsibility matrix maps roles to the project assignments. Answer option B is incorrect. A RACI chart is a responsibility assignment matrix using the legend of responsible, accountable, consult, and inform.
Reference: Chapter 5. A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth Edition, ISBN.9781933890517, Section 5.3.3.1.