what other documentation will need to be updated as an output of risk response planning?

Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Breakdown Structure

B.
Lessons learned

C.
Scope statement

D.
Technical documentation

Explanation:

The technical documentation should also be updated as new information comes available through the application of risk response planning, technical approaches, and physical deliverables. Answer option B is incorrect. Lessons learned is not an output of the risk response planning process. Answer option C is incorrect. The project scope statement is not updated as a part of risk response planning. Answer option A is incorrect. The risk breakdown structure is not a document that is updated as an output of risk response planning.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"