Which of the following is not a part of Identify Risks process?

Which of the following is not a part of Identify Risks process?

PrepAway - Latest Free Exam Questions & Answers

A.
System or process flow chart

B.
Influence diagram

C.
Decision tree diagram

D.
Cause and effect diagram