Where can a project manager find risk-rating rules?

Where can a project manager find risk-rating rules?

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assets

B.
Risk probability and impact matrix

C.
Risk management plan

D.
Enterprise environmental ors

Explanation:

Risk-rating rules define how the scoring of risk events will be defined during qualitative and quantitative analysis. The rules are pre-defined for the project manager and are a part of organizational process assets.

Answer option D is incorrect. The risk-rating rules are not defined in the enterprise environmental ors.

Answer option C is incorrect. The risk management plan does define the processes used in the project risk management knowledge area, but the risk-rating rules are defined in the organizational process assets.

Answer option B is incorrect. The risk-rating rules are applied to the risk probability and impact matrix, not part of the matrix itself.