PrepAway - Latest Free Exam Questions & Answers

Which of the following would require that the project risk register be updated?

Which of the following would require that the project risk register be updated?

PrepAway - Latest Free Exam Questions & Answers

A.
A qualitative risk analysis is performed

B.
A stakeholder has concerns about material delays

C.
The risk management plan is created

D.
Increased costs for required materials


Leave a Reply