Which of the following is the MOST likely action the project manager should take?

A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?

PrepAway - Latest Free Exam Questions & Answers

A.
Issue a change request to the change control board to select a different vendor from the qualified sellers list and request early termination of the current vendors contract.

B.
Call a project team meeting to discuss the risk and communicate the issue directly with the project sponsor.

C.
Contact the vendor and request a thorough review of the products architecture.

D.
Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor.