PrepAway - Latest Free Exam Questions & Answers

Which of the following should the project manager do FIRST to complete the project on time?

A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?

PrepAway - Latest Free Exam Questions & Answers

A.
Lower the quality standards for the finished product.

B.
Analyze the impact of the change.

C.
Eliminate 10 percent of the projects resources.

D.
Document the approved change request.


Leave a Reply