The formal process that must be performed at the end of the project to provide the final inspection of the pro

The formal process that must be performed at the end of the project to provide the final inspection of the product is called:

PrepAway - Latest Free Exam Questions & Answers

A.
methodology verification.

B.
scope verification.

C.
change verification.

D.
system verification.