Which of the following would be a direct output of the initiating process group? (Select Two).

Which of the following would be a direct output of the initiating process group? (Select Two).

PrepAway - Latest Free Exam Questions & Answers

A.
Project charter

B.
Project management plan

C.
Statement of Work (SOW)

D.
Work Breakdown Structure (WBS)

E.
Preliminary scope statement