In which of the following documents should this have been previously addressed?

During handover stage a customer of a particular project noticed the extended warranty from a particular vendor for a critical application has not been ordered. In which of the following documents should this have been previously addressed?

PrepAway - Latest Free Exam Questions & Answers

A.
Procurement management plan

B.
Project charter

C.
Staffing management plan

D.
Risk management plan