In order to determine project status, which of the following should the project manager do? (Select Two).

A new project manager has been assigned to a high profile project. In order to determine project status, which of the following should the project manager do? (Select Two).

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the key stakeholders for the project status.

B.
Leave a voicemail message to key personnel requesting the project status.

C.
Schedule a meeting with the team members to determine the project status.

D.
Send an email to the team members to request project status reports.

E.
Schedule a meeting with the project sponsor to determine the project status.