Which of the following would be the FIRST action?

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the project plan to accommodate the changes.

B.
Perform an impact analysis.

C.
Organize a stakeholder meeting to review the changes.

D.
Change the project scope to reflect the change request.