A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?

PrepAway - Latest Free Exam Questions & Answers

A.
Stakeholder analysis

B.
Risk assessment

C.
Audit review

D.
Phase gate