In which of the following documents should these requirements be included?

A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications management plan

B.
Cost management plan

C.
Project charter

D.
Contract management plan