A project manager is performing activity sequencing. The project manager is only using start to finish dependencies. Dummy activities are being utilized to define all logical relationships. Which of the following methods is the project manager demonstrating?

PrepAway - Latest Free Exam Questions & Answers

A.
Precedence Diagramming Method (PDM)

B.
Critical Chain Method (CCM)

C.
Arrow Diagramming Method (ADM)

D.
Critical Path Method (CPM)