PrepAway - Latest Free Exam Questions & Answers

Which of the following describes a work breakdown structure (WBS) dictionary?

Which of the following describes a work breakdown structure (WBS) dictionary?

PrepAway - Latest Free Exam Questions & Answers

A.
A high level requirements document used to create the WBS.

B.
An alphabetical listing of WBS components detailing their associated project schedule dependencies.

C.
An organizational reference defining how WBS levels must be decomposed.

D.
A supporting document that provides more detail for the WBS components.


Leave a Reply